You can not select more than 25 topics
Topics must start with a letter or number, can include dashes ('-') and can be up to 35 characters long.
229 lines
7.7 KiB
229 lines
7.7 KiB
15 years ago
|
<chapter id="definitions">
|
||
|
<chapterinfo>
|
||
|
<authorgroup>
|
||
|
<author>
|
||
|
<firstname>Anne-Marie</firstname>
|
||
|
<surname>Mahfouf</surname>
|
||
|
<affiliation>
|
||
|
<address><email>annma@kde.org</email></address>
|
||
|
</affiliation>
|
||
|
</author>
|
||
|
<author>
|
||
|
<firstname>Raphael</firstname>
|
||
|
<surname>Langerhorst</surname>
|
||
|
<affiliation>
|
||
|
<address><email>raphael.langerhorst@kdemail.net</email></address>
|
||
|
</affiliation>
|
||
|
</author>
|
||
|
<!-- TRANS:ROLES_OF_TRANSLATORS -->
|
||
|
</authorgroup>
|
||
|
</chapterinfo>
|
||
|
<title>Definitions</title>
|
||
|
|
||
|
<sect1 id="gantt">
|
||
|
<title>Gantt charts</title>
|
||
|
<para>A Gantt chart is a popular type of bar chart, that aims to show the timing
|
||
|
of tasks or activities as they occur over time. Although the Gantt chart did not
|
||
|
initially indicate the relationships between tasks this has become more
|
||
|
common in current usage as both timing and interdependencies between tasks can
|
||
|
be identified.
|
||
|
</para>
|
||
|
<para>
|
||
|
In project management, a Gantt chart can show when the project terminal elements
|
||
|
start and finish, summary elements (shown) or terminal element dependencies (not
|
||
|
shown). A terminal element is defined as the smallest task tracked as part of
|
||
|
the project effort. The tasks are displayed on a page as bars. The page is laid
|
||
|
out such that time increases as you move across the page. A task's start
|
||
|
time/date is indicated by the point on the page the bar starts, and it's
|
||
|
duration is indicated by the length of the bar.
|
||
|
</para>
|
||
|
<para>
|
||
|
Since the initial introduction of Gantt charts, they have become an industry
|
||
|
standard as a key project management tool for representing the phases, tasks and
|
||
|
activities that are scheduled as part of a project Work Breakdown Structure
|
||
|
(WBS) or timeline of tasks.
|
||
|
</para>
|
||
|
<para>
|
||
|
The initial format of the chart was developed by Henry L. Gantt (1861-1919) in
|
||
|
1910 (see <quote>Work, Wages and Profit</quote> by H. L. Gantt, published by The
|
||
|
Engineering Magazine, NY, 1910).
|
||
|
</para>
|
||
|
</sect1>
|
||
|
|
||
|
<sect1 id="wbs">
|
||
|
<title>Work Breakdown Structure (WBS)</title>
|
||
|
<para>
|
||
|
In project management, a work breakdown structure (WBS) is an exhaustive,
|
||
|
hierarchical (from general to specific) tree structure of deliverables and tasks
|
||
|
that need to be performed to complete a project.
|
||
|
</para>
|
||
|
<para>
|
||
|
The purpose of a WBS is to identify terminal elements (the actual items to be
|
||
|
done in a project). Therefore, WBS serves as the basis for much of project
|
||
|
planning.
|
||
|
</para>
|
||
|
<para>A useful rule of thumb is that any project can be broken down into
|
||
|
between 10 and 20 tasks.
|
||
|
</para>
|
||
|
<para>
|
||
|
Work breakdown structure is a very common project management tool. Many United
|
||
|
States government statements of work require work breakdown structures.
|
||
|
</para>
|
||
|
<para>See the <xref linkend="configure-wbs" /> section to learn how to
|
||
|
configure your WBS.
|
||
|
</para>
|
||
|
</sect1>
|
||
|
|
||
|
<sect1 id="float">
|
||
|
<title>Float</title>
|
||
|
<para>
|
||
|
Float in project management is the amount of time that a terminal element in a
|
||
|
project network can be delayed by, without causing a delay to:
|
||
|
<itemizedlist>
|
||
|
<listitem><para>subsequent terminal elements (free float)</para></listitem>
|
||
|
<listitem><para>project completion date (total float).</para></listitem>
|
||
|
</itemizedlist>
|
||
|
Float is sometimes also called slack.
|
||
|
</para>
|
||
|
</sect1>
|
||
|
|
||
|
<sect1 id="task">
|
||
|
<title>Task</title>
|
||
|
<para>
|
||
|
A task is a part of a project that needs to be accomplished within a defined
|
||
|
period of time. Tasks can be linked together to create Dependencies.
|
||
|
</para>
|
||
|
<para>
|
||
|
Tasks take place over a period of time and generally consume resources.
|
||
|
</para>
|
||
|
<para>
|
||
|
A task is termed critical when it has zero or negative float.
|
||
|
</para>
|
||
|
<para>
|
||
|
In &kplato;, each task has a task ID, a name and a responsible person.
|
||
|
The timing, the cost and the assigned resources can also be set
|
||
|
in the <guilabel>Task Settings</guilabel>dialog.
|
||
|
</para>
|
||
|
<para>A subtask is any node in the WBS tree that has a task as its
|
||
|
parent.</para>
|
||
|
|
||
|
</sect1>
|
||
|
|
||
|
<sect1 id="resource">
|
||
|
<title>Resource</title>
|
||
|
<para>
|
||
|
A resource is an item required to complete a task. Resources can be
|
||
|
people, equipment, facilities, funding or anything else needed to perform the
|
||
|
work of a project. Resources can have a limited time availability (&ie; an
|
||
|
employee that works 8 hours a day, 5 days a week).
|
||
|
</para>
|
||
|
<para>The availability is
|
||
|
defined by <link linkend="calendar">calendars</link>.
|
||
|
</para>
|
||
|
<para>
|
||
|
In &kplato; resources are either persons (work) or machines/devices (material).
|
||
|
</para>
|
||
|
</sect1>
|
||
|
|
||
|
<sect1 id="calendar">
|
||
|
<title>Calendars</title>
|
||
|
<para>
|
||
|
A calendar defines at what time a <link linkend="resource">resource</link>
|
||
|
is available.
|
||
|
</para>
|
||
|
<para>
|
||
|
Calendars can be either a regular working week or special working times
|
||
|
that can be individually defined for each day. This allows for very subtle
|
||
|
control over the availability of resources.
|
||
|
</para>
|
||
|
<para>
|
||
|
Every <link linkend="resource">resource</link> is usually connected to a
|
||
|
calendar.
|
||
|
</para>
|
||
|
<para>
|
||
|
In &kplato; you can even use hierarchical calendars.
|
||
|
</para>
|
||
|
</sect1>
|
||
|
|
||
|
<sect1 id="milestone">
|
||
|
<title>Milestone</title>
|
||
|
<para>
|
||
|
A milestone is a scheduled event signifying the completion of a major
|
||
|
deliverable or a set of related deliverables (usually marking the end of a
|
||
|
period). A milestone is an activity with zero duration and no effort &ie; there
|
||
|
is no work associated with a milestone. It is a flag in the workplan to signify
|
||
|
some other work has completed.
|
||
|
</para>
|
||
|
<para>
|
||
|
Usually a milestone is used as a project checkpoint to validate how the project
|
||
|
is progressing and revalidate work. Milestones are also used as high-level
|
||
|
snapshots for management to validate the progress of the project. In many cases
|
||
|
there is a decision to be made at a milestone.
|
||
|
</para>
|
||
|
</sect1>
|
||
|
|
||
|
<sect1 id="critical-path">
|
||
|
<title>Critical path</title>
|
||
|
<para>A path is a series of connected tasks. In project management, a
|
||
|
critical path is the sequence of project network terminal elements with the
|
||
|
longest overall duration, determining the shortest time to complete the project.
|
||
|
</para>
|
||
|
<para>
|
||
|
The duration of the critical path determines the duration of the entire project.
|
||
|
Any delay of a terminal element on the critical path directly impacts the
|
||
|
planned project completion date (i.e. there is no float on the critical path).
|
||
|
For example, if a task on the critical path is delayed by one day, then the
|
||
|
entire project will be delayed by one day (unless another task on the
|
||
|
critical path can be accelerated by one day).
|
||
|
</para>
|
||
|
<para>
|
||
|
A project can have several, parallel critical paths. An additional parallel path
|
||
|
through the network with the total duration just shorter than the critical path
|
||
|
is called a sub-critical path.
|
||
|
</para>
|
||
|
<para>
|
||
|
Originally, the critical path method considered only logical dependencies among
|
||
|
terminal elements. A related concept is the critical chain, which adds resource
|
||
|
dependencies.
|
||
|
</para>
|
||
|
<para>
|
||
|
The critical path method was invented by the DuPont corporation.
|
||
|
</para>
|
||
|
</sect1>
|
||
|
|
||
|
<sect1 id="scheduling">
|
||
|
<title>Scheduling</title>
|
||
|
<para>
|
||
|
Scheduling is the process of creating a project schedule based on the project
|
||
|
data like <link linkend="task">tasks</link>,
|
||
|
<link linkend="resource">resources</link> and
|
||
|
<link linkend="calendar">calendars</link>. The result can be viewed in a chart,
|
||
|
like a <link linkend="gantt">gantt chart</link>. &kplato; can also generate
|
||
|
reports for a project.
|
||
|
</para>
|
||
|
<para>
|
||
|
There are usually various scheduling modes, like optimistic, expected and
|
||
|
pessimistic scheduling. When creating a task the additional estimation
|
||
|
percentage
|
||
|
for optimistic and pessimistic scheduling can be set. These settings are then
|
||
|
used for the various scheduling modes.
|
||
|
</para>
|
||
|
<para>
|
||
|
When scheduling a project with &kplato;, you can choose between optimistic,
|
||
|
expected and pessimistic scheduling.
|
||
|
</para>
|
||
|
</sect1>
|
||
|
|
||
|
</chapter>
|
||
|
|
||
|
<!--
|
||
|
Local Variables:
|
||
|
mode: sgml
|
||
|
sgml-parent-document: ("index.docbook" "book" "chapter")
|
||
|
sgml-minimize-attributes:nil
|
||
|
sgml-general-insert-case:lower
|
||
|
sgml-indent-step:0
|
||
|
sgml-indent-data:nil
|
||
|
End:
|
||
|
-->
|